Indicative project timeline

Since we last spoke to you, there have been some changes to our indicative timeline.

Please see below for the latest information.

Demolition programme

Design programme

Winter 2023 / 2024

Spring 2024

Summer 2024

Autumn 2024

2025

Winter 2025/26

2026 - 2028

Design team appointed

Planning application decision for demolition works

Meet the Demolition Contractor event

Meet the design team event

Site set up and hoarding

Demolition works start

First design drop-in for residents and neighbours

Demolition works complete

Second design drop-in and workshop

Working with planners and key stakeholders

to develop the designs

Final pre-planning design drop in for residents and neighbours

Planning application for new homes submitted

Planning approval for designs granted (to be confirmed)

2027: Earliest construction start on site (to be confirmed)

2028: Earliest construction completion (to be confirmed)

Artwork by local children installed on site hoarding

This star indicates where we are now.

Please note this timeline is indicative and subject to change, we will keep you updated.